An international project team consists of local and overseas team members. The local team is responsible for integrating the projects work outputs. During the first integration phase, the need for a pre-validation of work outputs is identified, which will impact the
projects cost and schedule.
projects cost and schedule.
What should the project manager do next?
A. Perform a root cause analysis of the work outputs.
B. Update the responsibility assignment matrix (RAM).
C. Issue a change request to update the project management plan.
D. Update the work breakdown structure (WBS) to include the pre-validation activities.