Project Management Professional (PMP) Exam Practice – Question0779

A team member realizes that a technical update will improve a products performance. What should the team member do before implementing the update?


A.
Include new scope in the network breakdown structure (WBS).
B. Communicate with the project manager.
C. Document the change in the issue log.
D. Generate a change request.

Correct Answer: B