Due to commitments to another project, an accountant fails to deliver an important report. What should the project manager have referenced to avoid this?
A. Responsible, accountable, consult, and inform (RACI) matrix
B. Timesheets
C. Resource allocation plan
D. Resource calendar
A. Responsible, accountable, consult, and inform (RACI) matrix
B. Timesheets
C. Resource allocation plan
D. Resource calendar