Project Management Professional (PMP) Exam Practice – Question0783

A projects schedule indicates that activity A has a duration of five days, activity B has a duration of two days, and activity C has a duration of three days. Activity D has mandatory dependencies on activities A, B, and C.

What is the free float of activity B?


A.
10 days
B. 5 days
C. 3 days
D. 2 days

Correct Answer: C