Project Management Professional (PMP) Exam Practice – Question0785

A senior customer representative contacts a team member and requests a change to a functionality that is already developed. The team member discusses this with the team lead, and they agree that the change can be implemented. Although it will cause an
impact to the schedule, the team implements the change.

What is this an example of?


A.
Scope creep
B. Change request
C. Stakeholder management
D. Team cooperation

Correct Answer: A