Project Management Professional (PMP) Exam Practice – Question0787

An unforeseen issue results in the need to procure a new piece of machinery critical for meeting quality specifications. From where may the necessary funds be obtained?


A.
Key stakeholders
B. Management reserve
C. Contingency reserve
D. Project sponsor

Correct Answer: B