Project Management Professional (PMP) Exam Practice – Question0788

A project manager assumes a strategic project that has been ongoing for two years. Project team members are located in different countries, and communication among them is complex due to language and time-zone differences. The project manager wants to
obtain valid information about team members responsibilities and where the work is to be performed.

To what document should the project manager refer?


A.
Enterprise environmental factors
B. Activity attributes
C. Communications management plan
D. Work breakdown structure (WBS)

Correct Answer: D