A project manager determines that a project will be behind schedule and over budget as its current pace. If tasks must be performed sequentially, what scheduling technique should be used to get the project schedule back on track?


A.
Fast tracking
B. Critical path method (CPM)
C. Schedule forecast
D. Crashing

Correct Answer: D