Project Management Professional (PMP) Exam Practice – Question0790

A functional manager informs the project manager that a specific resource must be immediately transferred to another project. What should the project manager do?


A.
Update the resource calendar to reflect the transfer
B. Brief the sponsor on the risk
C. Ask the functional manager to allocate someone else for that project.
D. Negotiate with the functional manager to delay the transfer.

Correct Answer: B