Project Management Professional (PMP) Exam Practice – Question0800

A projects cost performance index (CPI) is 1.05 and its schedule performance index (SPI) is 0.95. Based on this information, what is the result of the project?


A.
Behind schedule and over budget
B. Behind schedule and within budget
C. Ahead of schedule and within budget
D. On schedule and over budget

Correct Answer: B