Project Management Professional (PMP) Exam Practice – Question0801

During the third year of a companys multiyear project, a small company is acquired. New project stakeholders are now identified, who begin suggesting several project changes.
What should the project manager use to manage these stakeholders recommendations?


A.
Change log
B. Project charter
C. Stakeholder register
D. Risk register

Correct Answer: C