Project Management Professional (PMP) Exam Practice – Question0804

A company is developing a new drug. Regulatory feedback indicates that a budget increase of 20 percent for additional work is required before the project can move to the next phase.
What should the project manager do?


A.
Initiate a change request.
B. Update the risk management plan.
C. Check the current outsourcing contracts.
D. Communicate the situation to the sponsor.

Correct Answer: B