A project manager conducts weekly, face-to-face meetings with a local project team to obtain status updates and inform the team of changes. Midway through the project, a virtual development team is added to handle some additional scope.
Before updating the communications management plan, what should the project manager do?


A.
Schedule a separate weekly call with the virtual development team.
B. Email the weekly meeting minutes to the virtual development team.
C. Add a daily teleconference to the schedule.
D. Update the stakeholder register.

Correct Answer: D