Project Management Professional (PMP) Exam Practice – Question0806

A project manager in a weak matrix organization notices that a resource is behind schedule on a project task. The project manager discovers that this resource was assigned to two other projects by the line manager.
What should the project manager do?


A.
Ask for a replacement.
B. Request that the resource be released from the other projects.

C. Schedule a meeting to prioritize the projects.
D. Ask the resource to work overtime.

Correct Answer: C