Project Management Professional (PMP) Exam Practice – Question0807

A key stakeholder is concerned about a critical risk that may cause the project to run over budget. The project manager wants to share the mitigation plan with the stakeholder.
What should the project manager do first?


A.
Check the organizational chart to determine the stakeholders department.
B. Review the risk register to identify the mitigation plan.
C. Identify which deliverable in the work breakdown structure (WBS) will be affected by the risk.
D. Consult the communications management plan to identify how to inform the stakeholder.

Correct Answer: B