Project Management Professional (PMP) Exam Practice – Question0808

A product development manager, who is unsure of an initial prototypes requirements, is upset to learn that it must be completed in two months.
What should the project manager have done to avoid this?


A.
Obtained the required resource from the procurement manager
B. Ensured that the right resources were assigned to the project
C. Included the product development manager in the communications management plan
D. Obtained stakeholder agreement on the projects schedule and deliverables

Correct Answer: D