A project manager has just completed a stakeholder engagement meeting where many points for discussion were deferred. The project manager must provide a response to the stakeholders at next months meeting.
What should the project manager do next?


A.
Update the risk register and prioritize the deferred points from the stakeholder engagement meeting.
B. Revise the budget and schedule estimates to include the deferred points requested by the stakeholders.
C. Submit a change request for the deferred points to update the stakeholder engagement plan.
D. Document the deferred points in the issue log and assign them to responsible project team members.

Correct Answer: D