A project manager conducts an inquiry into the increase of scrapped material over the past quarter. The project manager assembles a team and proposes a project business case to overhaul the system.
What should the project manage use to justify and establish boundaries for validating the viability of this project?
A. Cost-benefit analysis
B. Questionnaires and surveys
C. Cost of quality (COQ) method
D. Benchmarking