Project Management Professional (PMP) Exam Practice – Question0818

Two project team members have a different understanding of the intent of a work package. What should the project manager do?


A.
Empower the team members to request clarification from the client.
B. Conduct a brainstorming session with the team.
C. Review the work breakdown structure (WBS) dictionary with the team members.
D. Tell the team members to refer to the work authorization system.

Correct Answer: C