A project stakeholder requested a scope enhancement that was not approved due to budget constraints. Two months later, the project manager learns that the budget has enough flexibility to enhance scope.
To resubmit the identical request, to what document should the project manager refer?
A. Change log
B. Issue log
C. Risk register
D. Stakeholder register
To resubmit the identical request, to what document should the project manager refer?