Project Management Professional (PMP) Exam Practice – Question0822

During risk analysis for a building renovation project, it is discovered that the building contains toxic materials that must be removed. What should the project manager do to mitigate this risk using the risk transference strategy?


A.
Increase the management reserves to address the potential impact of additional time and cost.
B. Ask the client to remove the toxic materials and exclude this work from the contract.
C. Train personnel how to remove the toxic materials and then perform the work.
D. Hire a contractor to perform the work.

Correct Answer: D