A project is scheduled for implementation during the next three months. However, the key stakeholder wants to complete the project sooner in order to mitigate a regulatory compliance risk.
What should the project manager do?
A. Fast track the schedule.
B. Follow the change control process.
C. Reprioritize project timelines and update the schedule.
D. Crash the schedule.
What should the project manager do?
A. Fast track the schedule.
B. Follow the change control process.
C. Reprioritize project timelines and update the schedule.
D. Crash the schedule.