During project execution, several concerned stakeholders confront the project manager with concerns. The project manager discovers that these stakeholders expectations were unrecorded and, hence, unmet.
What should the project manager have consulted to avoid this?


A.
Communications management plan
B. Project charter
C. Stakeholder analysis
D. Stakeholder engagement plan

Correct Answer: D