A functional manager complains that an employee is involved in too many project meetings, wasting valuable time that could be used for other responsibilities. To what document should the project manager refer to address this?
A. Work breakdown structure (WBS)
B. Resource calendar
C. Network diagram
D. Work performance report
A. Work breakdown structure (WBS)
B. Resource calendar
C. Network diagram
D. Work performance report