Due to the use of a new technology, a milestone on a projects critical path is missed. What should the project manager do to calculate a new end date?


A.
Reestimate the remaining work with the team.
B. Base it on the current cost performance index (CPI).
C. Use the current schedule performance index (SPI).
D. Multiply the SPI by the CPI.

Correct Answer: C