A project has virtual teams in different geographic areas that are working on the same deliverables. Due to the project members unavailability for conference calls, some milestones have been unmet.
What should the project manager do to resolve this matter and prevent future issues?


A.
Create and keep the resource calendar updated and shared with team members
B. Ask the project teams to allocate more resources.
C. Perform an analysis, and revise the action plan for resource allocation.
D. Request that the functional team manager monitors team members availability.

Correct Answer: A