Project Management Professional (PMP) Exam Practice – Question0837

During a project's execution phase, the project manager receives notice from environmental authorities to stop work. What should the project manager have done to avoid this?


A.
Defined a detailed scope of work
B. Developed a comprehensive project management plan
C. Identified project risks
D. Identified stakeholders

Correct Answer: C