During project execution, a project team develops a new response for an existing risk that will reduce the schedule by 30 days. What document should the project manager update?
A. Work breakdown structure (WBS)
B. Risk breakdown structure (RBS)
C. Mitigation plan
D. Risk register
A. Work breakdown structure (WBS)
B. Risk breakdown structure (RBS)
C. Mitigation plan
D. Risk register