During project execution, a project manager learns that a team member's functional manager believes they should not execute a certain task.
What document should the project manager review to resolve this?
A. Responsibility assignment matrix (RAM)
B. Work breakdown structure (WBS)
C. Organizational chart
D. Resource management plan
What document should the project manager review to resolve this?
A. Responsibility assignment matrix (RAM)
B. Work breakdown structure (WBS)
C. Organizational chart
D. Resource management plan