A project manager receives an approved change request related to a project's governance framework. What should the project manager do to implement this change?


A.
Revisit the plan project process and update all planning documents affected by the change.
B. Re-estimate the durations of project activities affected by the change.
C. Put the project on hold until the impact of the change can be assessed.
D. Submit the change request to the project steering committee for approval.

Correct Answer: D