Project Management Professional (PMP) Exam Practice – Question0845

During the execution of a US$20 million project in a balanced matrix structure, a subject matter expert (SME) is pulled by their department manager. What should the project manager do to complete the project on time?


A.
Update the resource management plan
B. Negotiate with the department manager for a replacement.
C. Escalate the issue to the department manager's line manager.
D. Refer the issue to the project management office (PMO).

Correct Answer: B