Project Management Professional (PMP) Exam Practice – Question0846

During the execution of an IT project, a project manager warns of the possibility that the main server may fail due to constant, local-area electrical outages. The project manager signs a contract to rent an additional server from a local company.
What strategy is the project manager using?


A.
Share
B. Transfer
C. Mitigate
D. Enhance

Correct Answer: C