Although previously identified project risks have not yet materialized, a project appears to be in trouble. The project manager implements the appropriate risk responses, but this fails to bring the project back on track.
What should the project manager do next?


A.
Transfer the risks.
B. Update the risk register.
C. Request a risk audit.
D. Analyze the risks.

Correct Answer: B