Project Management Professional (PMP) Exam Practice – Question0850

A project's original budget at completion (BAC) was calculated as US$100,000, but the estimate at completion (EAC) is US$120,000. If the schedule performance index (SPI) is equal to 1, what is the cost performance index (CPI)?


A.
Equal to 1.2
B. Less than 1
C. Equal to 1
D. Greater than 1

Correct Answer: B