Project Management Professional (PMP) Exam Practice – Question0852

After relocating an entire team to a remote project site, the project manager discovers a discrepancy between the project contract and the project scope. What should the project manager do to avoid delays and the underutilization of the relocated team?


A.
Discard the contract and proceed with the project scope.
B. Issue a change request to correct the contract.
C. Perform a cost analysis and bill to the customer.
D. Evaluate the impact of the discrepancy and report the findings to the sponsor.

Correct Answer: D