Project Management Professional (PMP) Exam Practice – Question0853

A lengthy, ongoing project exhausts a project team. Due to deadline issues, the project manager needs to encourage team members.
What should the project manager do?


A.
Review the project charter and propose extending the project schedule.
B. Provide more recognition and rewards to team members.
C. Discuss the situation with the team.
D. Request additional resources.

Correct Answer: B