A sponsor proposes a project scope change that is popular with the project team and key stakeholders. What should the project manager do?
A. Follow the scope change request process.
B. Notify stakeholders of the change.
C. Update the project requirements.
D. Modify the work breakdown structure (WBS).
A. Follow the scope change request process.
B. Notify stakeholders of the change.
C. Update the project requirements.
D. Modify the work breakdown structure (WBS).