Project Management Professional (PMP) Exam Practice – Question0855

A global project is meeting schedule, scope, and cost requirements. Then, a labor strike in one of the countries causes a key resource to become unavailable.
How can the project manager resolve this?


A.
Allow the team to work overtime.
B. Negotiate a schedule extension with the customer.
C. Implement the planned risk responses.
D. Update the risk management plan.

Correct Answer: C