Project Management Professional (PMP) Exam Practice – Question0857

While preparing a project's third progress report, the project manager identifies that the project will experience delays due to late material deliveries. The two previous project reports indicated that the project was on track.
What should the project manager do next?


A.
Discuss it with the project team to determine the most appropriate way to respond.
B. Add it to the issue log and include it in the project report.
C. Contact the procurement manager to expedite delivery of the material.
D. Escalate the issue to the project owner and request a schedule change.

Correct Answer: B