Project Management Professional (PMP) Exam Practice – Question0858

A project execution phase overlaps with a holiday in the country where the majority of team members are based. This phase is critical, and all team members are required to work through the holiday. This negatively impacts team morale.
What should the project manager have done to avoid this?


A.
Requested help from other teams based in other countries
B. Postponed project activities
C. Prepared the stakeholder engagement plan
D. Better developed the resource management plan

Correct Answer: D