Project Management Professional (PMP) Exam Practice – Question0859

A large risk to a project is identified, and the risk management plan is executed. Upon completion of the approved actions, what should the project manager do?


A.
Update the risk management plan.
B. Revise the project schedule and the budget.
C. Update the lessons learned.
D. Identify new risks, and monitor residual risks.

Correct Answer: C