Project Management Professional (PMP) Exam Practice – Question0860

A project team discovers an opportunity to enhance software without impacting the budget or schedule. The team makes the enhancement without proper documentation, which later causes production issues.
What process should have been conducted to prevent this?


A.
Control Schedule
B. Perform Qualitative Risk Analysis
C. Plan Scope Management
D. Perform Integrated Change Control

Correct Answer: D