Project Management Professional (PMP) Exam Practice – Question0861 Based on the project schedule, how much float is there for activity number 4? A. 0 days B. 4 days C. 7 days D. 9 days Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question0860Project Management Professional (PMP) Exam Practice – Question0862