Project Management Professional (PMP) Exam Practice – Question0862

After completing a project schedule, the project manager learns that the sponsor wants an earlier completion date without incurring additional costs. What technique can the project manager use to meet these requirements?


A.
Resource leveling
B. Fast tracking
C. Monte Carlo simulation
D. Crashing

Correct Answer: B