Project Management Professional (PMP) Exam Practice – Question0863

While reviewing the statement of work (SOW), two stakeholders disagree on what the project should include. What should the project manager do?


A.
Include the stakeholders comments for future reference in the project charter.
B. Meet with the two stakeholders to resolve the conflict and reach agreement.
C. Document the stakeholders opinions but include the remaining stakeholders input in final decision making.
D. Document the conflict in the issue log before participating in the development of the project charter.

Correct Answer: C