Project Management Professional (PMP) Exam Practice – Question0866

Due to increased price volatility, a vendor asks the project manager to make a price change that will affect the project contract. What should the project manager do next?


A.
Ask the change control board (CCB) for approval.
B. Execute the approved change.
C. Evaluate the impact, then update the risk register, project management plan, and budget.
D. Submit a change request and analyze the impact.

Correct Answer: D