Project Management Professional (PMP) Exam Practice – Question0868

When conducting procurements, what process should the project manager implement to obtain stakeholder agreement?


A.
Update Stakeholder Engagement Plan
B. Manage Stakeholder Engagement

C. Monitor and Control Project Work
D. Plan Procurement Management

Correct Answer: D