Project Management Professional (PMP) Exam Practice – Question0870

The implementation of a business requirement for an IT project impacts several applications. The application owner notices that changes to a function in application X can be started only upon completion of the development of a new feature in application Y.
This is an example of what dependency?


A.
Start-to-start (SS)
B. Finish-to-start (FS)
C. Start-to-finish (SF)
D. Finish-to-finish (FF)

Correct Answer: B