A project has been ongoing for a year. Early in the year, its schedule performance index (SPI) was 1.2; its most recent SPI is 0.7.
What did the project manager use to track and communicate this information?


A.
Project communications

B. Project management information system (PMIS)
C. Performance reporting
D. Variance analysis

Correct Answer: D