A project manager develops a risk breakdown structure (RBS) and divides it into four categories. Later, the team identifies a regulation issue with one of the customer's requirements.
In what category should this new risk be included?
A. Technical
B. Organizational
C. External
D. Project management
In what category should this new risk be included?
A. Technical
B. Organizational
C. External
D. Project management