A project manager develops a risk breakdown structure (RBS) and divides it into four categories. Later, the team identifies a regulation issue with one of the customer's requirements.
In what category should this new risk be included?


A.
Technical
B. Organizational
C. External
D. Project management

Correct Answer: C